Mammoet Completes Major Milestone for Gulf Coast LNG Export Terminal

Mammoet has completed a major milestone with the installation of the Main Cryogenic Heat Exchanger (MCHE), considered to be the heart of Train One, at a liquefaction project along the U.S. Gulf Coast.

The lift of the MCHE, which weighed a total of 650,000 lbs. (295 tonnes), was a dual lift utilizing a Terex-Demag CC-2800 crawler crane as the main crane and a Liebherr LR-1300sx crawler crane on the tail. The inclement weather was a source of many challenges including broadening the travel path for transport, smoothing the roads, and re-doing the crane pads and travel path after storms had moved through.

The project is currently comprised of three natural gas liquefaction trains with approved liquefied natural gas (LNG) export capacity of 1.7 billion cubic feet per day. When complete, it will be one of the largest LNG export terminals in the US.

“The combined efforts and hard work of all crews on site made this a safe and successful installation. The crews displayed an ‘adapt and overcome’ mentality to many obstacles to execute this operation in a truly professional fashion” said Randall Fox, Mammoet USA Senior Project Manager.

Learn more about Mammoet at their website.

Get the free newsletter

Sign up for news, trends and equipment for sale in the lifting and rigging industry.
By signing up you agree to our Terms of Use and Privacy Policy. You may unsubscribe at any time.

Latest Products For Sale

Type Description
Lifting Products
Hooks
1/2” Grade 70 clevis grab hooks
Lifting Products
Chains
1/2” Grade 70 chain 13 drums 200’ each (Make Offer)
Lifting Products
Hooks
3/8” Grade 70 clevis grab hooks
Lifting Products
Chains
3/8” Grade 70 chain 6 drums 400’ each (Make Offer)
Equipment Used 75’ pull test bed. Currently in 3 pcs. 25’ long would need to be…

News & Articles